Description of
Work:
|
SITE WORK AND RIDE FOUNDATION ONLY.
**QUEUE BUILDINGS, COVERED WALKWAY, MOTOR HOUSE, STATION HOUSE, MAINTENANCE BUILDING, TRANSFER HOUSE, UTILITY BUILDING & PHOTO BUILDING WILL NOT BE PERMITTED AT THIS TIME. THESE STRUCTURES ARE NOT INCLUDED IN THE SCOPE OF WORK AND WILL BE PERMITTED SEPARATELY.**
**PROPERTY ZONED ED. SEE GIS ZONING MAP IN OLE.**
3/6/19 Carrie West has been removed as contact and David Emler has been added. See Ole. **avaladez**
--- NO ELECTRICAL WORK PER DIANA BONELLI 3/7/2019 EMAIL - SITE WORK ONLY - BRAD JOHNSON - 3/7/2019 ---
***3/12/19 - Retaining wall shall be submitted as a separate permit. D. Artalejo***
**3/25/19 - CUST PLANS READY FOR P/U IN BIN Q-35/36 - CUST NOTIFIED - (C.DELGADO) **
**12/18/19 --CUSTOMER NOTIFIED PLANS IN BIN P-43 WILL BE DISCARDED BY 01/03/2020 (A.SANCHEZ) **
**1/7/19- DO NOT DISCARD PLANS. CUST NOTIFIED OUR PERMIT COUNTER THAT THE PROJECT IS ON GOING AND WILL PICK UP PLANS.** A.SANCHEZ
**1/9/20- PLANS PICKED UP BY TODD - (C.DELGADO) ** |